swanson

January 2023

Preparing for 2023. The garage is full of Insulated Concrete Forms (ICFs), a pallet of cement, concrete dye, sealant, and more. We won’t be completely ready, but it should be better than last year. At the end of the summer in 2022, we bought a truck. It has a dumptruck bed so we can haul […]

January 2023 Read More »

August 31 2022

Finally, we are on to the cistern. With help from Hunter and Steve, we got the base poured. Logan hauled the mixer/pump up to the cistern site with the excavator. Motion again! Steve and Hunter helped make the floor pour a smooth operation.

August 31 2022 Read More »

August 28 2022

Logan returned from Alabama, but there was a delay in getting an excavator. And of course there is the never ending saga of getting gravel. During this time we made progress with the spring and spring box, plus I showed the road to another trucking company who decided not to deliver gravel. The good news

August 28 2022 Read More »

August 17 2022

Nash and Logan both departed, so only Wylie and I have been working for the last two weeks, which means progress has slowed considerably. Still, progress has been made, plus Logan will be coming back soon to hopefully kick the project back into high gear.

August 17 2022 Read More »

August 6 2022

The crew of Logan, Sabrina, and Nash have left and thus there is a lull in the project. My knee finally said “ENOUGH” and I could barely get up and down the stairs for several days. We still have not gotten gravel delivered for the next concrete pours. The good news is that Logan will

August 6 2022 Read More »

July 26 2022

With Mark staying to help, we’ve made good progress and have poured the walls of the spring box. This involved operating the mixer/pump for the first time plus some hard labor. So far, so good. Stages of building the form for the spring box. We started with 2-inch foam insulation walls, then put a rebar

July 26 2022 Read More »

July 21 2022

Disaster! Much has happened, but the biggest event was we had a serious accident. Logan was badly cut and broke a bone in his finger, resulting in a trip to the emergency room. The accident occurred while trying to fabricate a wooden spoon with a circular saw, with assistance from Mark — everyone involved feels

July 21 2022 Read More »

July 17 2022

We are largely held up because we do not have gravel nor have we gotten the cement mixer/pump hauled up the mountain and positioned. This probably isn’t that bad, as several projects have been polished. The waterline is buried from the spring box location to the cistern location, and then from the cistern to the

July 17 2022 Read More »

July 9 2022

The waterline is essentially done. The road for the concrete mixer/pump is mostly in shape. Now we’re just waiting on the gravel and getting the mixer/pump up the mountain. The last part of the line was tricky due to rock shelves the line had to crawl over. We insulated the line for much of the

July 9 2022 Read More »

July 4 2022

A week since last update Most of the work done this week was devoted to the waterline. The trench is now all but complete, although there are a few sections where Logan couldn’t get it very deep due to rock. Our plan is to insulate the line in those places and then mound up dirt.

July 4 2022 Read More »

June 2 2022

We checked out the road since its been smoothed out with the bulldozer and it looks ready to go until the next rain. Today we had a few extra hands with Scott and Orion to help out with toting chainsaws, lumber, etc. up to the site. Wiley and Orion were super excited to carry the

June 2 2022 Read More »

May 26 2022

Logan and Sabrina arrived and we hiked up to take a look. It’s supposed to rain for several days, and then there is going to be road construction for a few days, so we may not be able to get working until early June. Wylie reacted to this by practicing his hair combing. 

May 26 2022 Read More »