November 17 2024

The posts will be fewer with winter coming on, and progress is incremental as a rule. One HUGE development, however, is that Todd came up and got the solar hot water system running. This is important because it keeps the cellar warm where there are pipes that could freeze and batteries that need to be …

November 17 2024 Read More »

October 26 2024

Tom came over for a few days and we made great progress on the ceiling. Among other things, Tom can still work like crazy and he wore me out. Niko came up and had a frustrating time, but we do have electricity from the solar system and there was progress with the solar hot water, …

October 26 2024 Read More »

October 20 2024

There has been some progress since my last post, but it’s just short of success in a couple of key areas as discussed below. Niko (left image) has been working on the solar electrical system and the solar hot water system. The electrical system has charged up the batteries to full capacity, a significant success. …

October 20 2024 Read More »

October 5 2024

Bits and Pieces Work is in a fairly relaxed mode, and thus progress is modest. Rather than continue with short posts, I will likely make infrequent posts unless something significant arises. One thing not documented in this post is that Niko made had his first visit to Skookum and we made some progress with the …

October 5 2024 Read More »

September 22 2024

Buttoning up With it possible for snow to fly any time, recent work has been devoted to buttoning up. But unlike previous years, rather than figuring on leaving Skookum alone over the winter months, I have been preparing for visits with work and play for the winter. Not a lot was done in the past …

September 22 2024 Read More »

September 7 2024

The Roof! This was another pretty good week, even if it doesn’t look like much. The cabin has had a “temporary” ridge cap made from 2 by 6’s and flashing tape since last fall. This week, with help from Tim, we finally put up the remaining fascia and rake flashing plus the ridge cap, something …

September 7 2024 Read More »

August 25 2024

After a nice break with a kayak and backpacking trip, progress continues at Skookum. The usual summary follows. Mark, Nash, Logan, and Randi spent a day at Skookum and made some positive additions. A new broom, a new ax, and best of all, a new table with a chess board and cribbage board built in. …

August 25 2024 Read More »

July 25 2024

I will be taking a break from work on Skookum to spend some time kayaking and backpacking. Below is an update of the progress and getting the place buttoned up for my break. Meg helped me put up another 10 ft of wainscoting and I do like the way it looks! The left photo shows …

July 25 2024 Read More »

July 15 2024

Another week and more progress. Some time ago I made loose arrangements to put up the solar systems and install the wood stove in July… and now it looks like neither of those will happen. I can still get the cabin ready for winter, but it’s going to take work later on, probably September or …

July 15 2024 Read More »

July 6 2024

This is another summary of several days of effort. There’s nothing dramatic here, just slow and steady progress. The above photos show the South, East, and North windows (from left to right) before (top) and after (bottom) sawing them open to their actual size. With the logs cut out it really changes the character. The …

July 6 2024 Read More »

June 30 2024

This post includes a mish-mash of progress from several trips to Skookum. Progress has been good, with the completion of the underlayer of the floor the biggest milestone. Tim and I had a great day when we nearly finished the underfloor. Tim is working on the frame (left photo) and we had all but two …

June 30 2024 Read More »

June 23 2024

This post is from several trips to Skookum, all with the goal of getting the cabin winterized. Tim Fry has been helping with the wood floor, and Wylie did a great job helping pour concrete (but we didn’t get any pictures because he ran the batteries out on my phone), and I even spent a …

June 23 2024 Read More »

June 6 2024

As the weather has improved progress has begun on the cabin again. Work will be a bit haphazard and not nearly as intense as last year. As a result the posts will likely be fairly random. This post covers three trips up to Skookum. Wylie and I took down the frames for the wall-tent floors …

June 6 2024 Read More »

May 18 2024

The season is starting MUCH earlier than last year. I drove all the way in with no problems, except a large tree has fallen across the road early on. Someone had cut enough of it out that I could sneak by. Wylie and I got a fair amount done and still got back in time …

May 18 2024 Read More »

April 30, 2024

Winter is waning, so I thought I would share some pictures of Skookum as spring begins. I have hiked in 3 times this winter on snowshoes, each trip taking about an hour. The photo above shows the cabin on Feb 17, 2024. The left photo shows my snowshoe track on a beautiful day in February, …

April 30, 2024 Read More »

November 5 2023

Last visit for the year? I made what might be the last visit to Skookum for the year, hiking in the mile and a half from the base of the jeep road with Phil Battle and his puppy Tilly. The snow from last week had mostly melted, making for a muddy trip. There were just …

November 5 2023 Read More »

October 29 2023

Buttoning up My posts have slowed down, and will slow down more as the winter months settle in. Since Logan left, I’ve been up to Skookum 3 times to tear down the camp and prepare for winter. I hope to get up there one more time, but overall things are pretty well set until  the …

October 29 2023 Read More »

October 9 2023

The roof! Putting the roof up consisted of first, putting up the SIP panels, which are 4 ft by 16 ft panels that are 1 ft thick (OSB sheeting on each side with foam insulation in the middle). As with pretty much everything else, we had never used these before. Then, based on some skimpy …

October 9 2023 Read More »

October 2 2023

A pretty good week The Alaskan mill is put away. The scribe is put away. The chainsaw work is almost done. All the logs are up. This week was all about getting the roof support system up. The purlins in particular were challenging, as they had some awkward bows that were hard to accommodate. Also, …

October 2 2023 Read More »

September 25 2023

Roof and Rain A major rain storm came in and cut this week short at Thursday. Mark and Logan worked on Tuesday, and then I went up on Wednesday, so we only got two days of work in. However, we’re working on the roof and it’s fun to see the progress. https://youtu.be/zYEQTfLPBoI Mark and Logan …

September 25 2023 Read More »

September 18 2023

Near Disasters and Progress This was a full week with Mark here, and following a tradition set last year, much progress was made and a (near) disaster occurred. The progress is described with the images below. The (near) disaster was that Logan cut himself with a chainsaw, which resulted in a trip to the Emergency …

September 18 2023 Read More »

September 11 2023

9/11 Anniversary — almost fitting I am posting this on the anniversary of the 9/11 attacks. This past week wasn’t that disastrous, although there were more near-misses than we should have had, as noted below. Progress was considerable, as all the SIP panels for the roof are on site, the steel for the roof is …

September 11 2023 Read More »

August 28 2023

Walls going up This week was all about putting up walls and we made good progress without major mishaps. We’re a bit over halfway done with the fourth row of logs out of six. As we refine our process we’re making faster progress and doing better work, although the approach is still not what anyone …

August 28 2023 Read More »

Augest 21 2023

Ramping up… I hope As usual, we didn’t get as far as I had hoped, but progress was made and nobody was hurt. A couple of Logan’s friends showed up, plus we got rained out for a day, so we only got about three and a half days of work but we completed the second …

Augest 21 2023 Read More »

August 14 2023

HUGE Sill Logs! This was our first work with logs, and of course you start with the bottom (sill) logs that are the most difficult, and also the biggest. Logan, cleverly, took most of this week off to spend with Sabrina, so Tom came over to take his place. The progress is described below, followed …

August 14 2023 Read More »

August 7 2023

Not much progress, but not zero progress Everything seemed to conspire against making progress this week. The weather was unusually wet, we swapped out the excavator for a telehandler (which took time), Sabrina arrived so Logan is taking some time off, my truck died (temporarily) in a highly inconvenient  spot, and of course there was …

August 7 2023 Read More »

July 31 2023

Too fast! Mistakes! And good luck? This week was ambitious and so we had to move fast. This led to mistakes, and of course problems happen even without making mistakes. And in the end we ran into a major problem… but at exactly the right time. As a result, we began a pivot and will …

July 31 2023 Read More »

July 24 2023

The original plan for this week was to backfill the cellar, set up and pour footings for the walls, and then work on the stem walls. We changed this by shifting to dirt work after the footings so we could access the main floor with the excavator for leveling. Also, I changed up the schedule …

July 24 2023 Read More »

July 17 2023

This week saw some progress, but it was also frustrating. The images below show the progress. The frustration was largely due to my ignorance of concrete and flawed thinking on what Wylie would like. The ignorance was that I didn’t figure on time needed for concrete to cure before backfilling. The flawed thinking was that …

July 17 2023 Read More »

July 7 2023

Logan arrived, and we have had a busy week, not without hiccups and dumb-ass attacks.  We finally finished up the cistern, applying 2 more coats of sealant. I used a fan with dryer venting that Wylie and I made to blow in fresh air before going into the cistern. Additionally, I parked the tractor over …

July 7 2023 Read More »

June 22 2023

Over the past week or so I have been trying to get going so we can hit the ground running when Logan arrives. Most of the supplies are ordered and the following images show the process of getting the new camp up. We dug holes to set posts, then built a simple 2 by 4 …

June 22 2023 Read More »

May 6 2023

There was plenty of melting since my last visit a month ago. Side by side photos shown below are dramatic.  May 6 April 9 The cistern appears to be in good shape. I need to get inside it to seal it in June. May 6 April 9 The tractor (covered in tarps) was almost buried …

May 6 2023 Read More »

April 9 2023

I hiked up to Skookum today and found — no surprise — LOTS of snow. The top of the cistern air vent is just under the tripod and about a foot out of the snow. I painted the air vent black and built a tripod to protect it from animals. The cistern last fall. The …

April 9 2023 Read More »

January 2023

Preparing for 2023. The garage is full of Insulated Concrete Forms (ICFs), a pallet of cement, concrete dye, sealant, and more. We won’t be completely ready, but it should be better than last year. At the end of the summer in 2022, we bought a truck. It has a dumptruck bed so we can haul …

January 2023 Read More »

September 15

I am a little out of sync with the posts. Lately nearly all the work has been devoted to the cistern, and we will soon be shutting down for the winter. The idea was to backfill as we poured to support the foam outer walls. Besides — can you believe it — we finally got …

September 15 Read More »

August 31

Finally, we are on to the cistern. With help from Hunter and Steve, we got the base poured. Logan hauled the mixer/pump up to the cistern site with the excavator. Motion again! Steve and Hunter helped make the floor pour a smooth operation.

August 28

Logan returned from Alabama, but there was a delay in getting an excavator. And of course there is the never ending saga of getting gravel. During this time we made progress with the spring and spring box, plus I showed the road to another trucking company who decided not to deliver gravel. The good news …

August 28 Read More »

August 17

Nash and Logan both departed, so only Wylie and I have been working for the last two weeks, which means progress has slowed considerably. Still, progress has been made, plus Logan will be coming back soon to hopefully kick the project back into high gear.

August 6

The crew of Logan, Sabrina, and Nash have left and thus there is a lull in the project. My knee finally said “ENOUGH” and I could barely get up and down the stairs for several days. We still have not gotten gravel delivered for the next concrete pours. The good news is that Logan will …

August 6 Read More »

July 26

With Mark staying to help, we’ve made good progress and have poured the walls of the spring box. This involved operating the mixer/pump for the first time plus some hard labor. So far, so good. Stages of building the form for the spring box. We started with 2-inch foam insulation walls, then put a rebar …

July 26 Read More »

July 21

Disaster! Much has happened, but the biggest event was we had a serious accident. Logan was badly cut and broke a bone in his finger, resulting in a trip to the emergency room. The accident occurred while trying to fabricate a wooden spoon with a circular saw, with assistance from Mark — everyone involved feels …

July 21 Read More »

July 17

We are largely held up because we do not have gravel nor have we gotten the cement mixer/pump hauled up the mountain and positioned. This probably isn’t that bad, as several projects have been polished. The waterline is buried from the spring box location to the cistern location, and then from the cistern to the …

July 17 Read More »

July 9

The waterline is essentially done. The road for the concrete mixer/pump is mostly in shape. Now we’re just waiting on the gravel and getting the mixer/pump up the mountain. The last part of the line was tricky due to rock shelves the line had to crawl over. We insulated the line for much of the …

July 9 Read More »

July 4

A week since last update Most of the work done this week was devoted to the waterline. The trench is now all but complete, although there are a few sections where Logan couldn’t get it very deep due to rock. Our plan is to insulate the line in those places and then mound up dirt. …

July 4 Read More »

June 22

We have since learned the hose clamps should be positioned with opposite pulls, but we’re not going to dig up the line to fix this. One of the many mistakes we have made, and hopefully this one is not too serious.

June 20, 2022

The concrete pump has finally arrived. On a cold day, Wylie had to wear a pair of Logan’s shorts for pants, which inspired a rather goofy dance.